Bally’s Secures $560 Million in New Financing as Chicago Casino Targets Spring Opening

Posted on: Last Updated: Views: 37
Lidia Moore

Author:

Expertise: US Gaming, European Gaming Industry, iGaming

Bally's has announced $560 million in new financing commitments as construction continues on its Chicago casino, which is targeting a spring 2027 opening.

CHICAGO – Bally’s announced $560 million in new financing commitments as it targets a spring 2027 opening for its permanent Chicago casino. The agreements aim to ease financial pressure on the operator, although the project’s hotel remains delayed and further approvals are required.

The financing package includes $500 million in proposed second-lien loans and an additional $60 million commitment from Gaming and Leisure Properties (GLPI). In its November 17 financing announcement, Bally’s said the agreements would improve liquidity and support further development of its $1.7 billion Chicago casino complex.

New Financing Targets Debt and Chicago Casino Development

The $500 million loan commitment comes from affiliates of Bally’s existing lenders and would provide net proceeds to repay outstanding debt and cover general corporate expenses. The separate $60 million commitment from GLPI is designated for additional development at Bally’s Chicago, bringing the real estate company’s total commitment to the project to $1 billion.

The GLPI funding remains subject to regulatory approval, while the wider financing arrangements require final documentation and other necessary approvals. Bally’s said the new commitments would help meet its cash flow requirements over the coming year.

The announcement follows months of questions about whether Bally’s could finance its permanent casino development. During a September Chicago City Council hearing, executives defended the project’s financing while aldermen questioned construction delays and the company’s ability to meet its obligations.

Financial Losses Continue to Raise Concerns

Despite the financing announcement, Bally’s Chicago continues to face financial challenges. Its latest quarterly filing with the Securities and Exchange Commission, submitted November 16, reported an $82.7 million net loss for the first nine months of 2026.

The filing showed approximately $110 million in revenue during the period, alongside $151.7 million in cash used for operating activities. Bally’s Chicago also reported an accumulated deficit of $240.5 million and approximately $7.6 million in cash as of September 30.

The subsidiary warned that its temporary casino at Medinah Temple had not generated sufficient operating cash to cover both ongoing operations and the remaining construction obligations. Management concluded that substantial doubt remained about its ability to continue as a going concern, despite receiving financial support assurances from its parent company.

Bally’s Corporation reported $807.6 million in consolidated third-quarter revenue, an increase of 21.7% year over year. However, the Chicago subsidiary’s financial position remains dependent on continued funding and the completion of additional financing arrangements.

Chicago Casino Opening Remains on Track, but Hotel Delayed

Bally’s continues to target spring 2027 for the permanent casino’s opening in Chicago’s River West neighborhood. However, the 34-story hotel and certain non-gaming amenities have been moved to a later development phase, with no confirmed opening date for the hotel.

The company slowed construction on several parts of the project in August amid a dispute with Chicago officials over the introduction of video gaming terminals at bars and restaurants. Bally’s argues that expanding these machines could divert gambling revenue from its casino and conflict with its host community agreement.

The dispute has gained renewed attention as Chicago’s first licensed video gaming terminal locations began operating this week. The Illinois Gaming Board has approved 78 establishments for video gaming, with several additional locations expected to launch before the end of 2026.

While Bally’s maintains its objections to the terminals, the company says the permanent casino remains on schedule. The additional GLPI commitment would support the phased introduction of restaurants and other amenities during 2027, rather than immediately restoring the original hotel opening plans.

The permanent property is expected to become one of Illinois’ largest casinos, with approximately 4,000 gaming positions and a range of dining and entertainment facilities once completed. Chicago officials have projected that the development could eventually generate around $200 million annually in local tax revenue, although that estimate depends on future operating performance.

Bally’s must now finalize its financing arrangements, secure the necessary regulatory approvals and complete the remaining casino construction. Whether the additional funding resolves its liquidity concerns and keeps the spring 2027 opening on schedule will become clearer as development progresses.